And the back-up plan is?Major Outage at PSAC 2
Fire & EMS Radios & Computers are down @11:30
prayer.And the back-up plan is?
That’s supposed to be the ‘back-up’ for PSAC at Metro Tech, so what’s the back-up for the back-up? 😵💫And the back-up plan is?
You mean the one known as the fail-safe plan?That’s supposed to be the ‘back-up’ for PSAC at Metro Tech, so what’s the back-up for the back-up? 😵💫
Everything was over the air. We survived. Although many Engines in Brooklyn had incidents where EMS was needed and not dispatched properlyAnd the back-up plan is?
The bell system and chalkAnd the back-up plan is?
This would never have happened if they were still running off the telegraph bells!The bell system and chalk
I hope that person is fired, not just not allowed to work on this equipment! According to the article the switch was very clearly marked, if he had read that instead of just automatically opening the cover and pushing the button the problem probably would not have occurred.![]()
Oops! FDNY contractor presses wrong button, shuts down NYC’s emergency dispatch system
Wednesday’s snafu at the FDNY’s MetroTech Center facility forced staffers to rely on ancient methods — pens, paper and telephones rather than digital systems.nypost.com
You would be firing the wrong person. The people that need to be fired are the ones that designed the equipment and the one that gave final approval.I hope that person is fired, not just not allowed to work on this equipment! According to the article the switch was very clearly marked, if he had read that instead of just automatically opening the cover and pushing the button the problem probably would not have occurred.